Olympiahalle, Munich

Extension of the existing hall floor and installation of a new floor slab in the Munich Olympia Hall. The engineering work is only a part of the enormous task of renovating the Olympia Hall, which will take a total of six years and not be completed until 2019. The problem is that the refurbishment work can only be done in the small time slot between July and the beginning of October each year when the hall is not required for events. For this reason, on-schedule work was absolutely top priority.


  • Demolition work: approx. 1,800 m²
  • Steel structure: approx. 20 tonnes
  • Floor slab: approx. 1,800 m²
  • Installation of cable channels

Construction period: June 2013 – September 2013